Cambridge St Umina Beach

New Builds

The Brief

​Project type was a knock down and rebuild of a custom architecturally designed home, designed and constructed to accommodate the clients request and lifestyle.

​We were contracted by a buyers agent to work on behalf of them from start to finish.​

​The brief was open plan space, decent size bedrooms with ensuites, natural appeal of timber flooring throughout with a beachy, hamptons style vibe to accomodate a couple of retirees who would like to enjoy their home and also be near the beach. They required a modern style kitchen and bathrooms, which flowed onto a spacious outdoor entertainment area, spacious garden and outdoor sauna.

Project Scope

Construction time for this project was initial engagement from client in Dec 2021. Commencement of work May 2022.

Handover on completion Dec 2022. (8 months construction, 12 months start- finish).

Overall construction costs – $900,000- $950,000.

Project cost which includes, architect, engineer, private certifier, Geotech engineer, Surveyor – $1,000,000 – $1,050,000.

Key Highlights & Takeaways